The project was staged in phases so the school could operate in their existing facility during construction. Phase one consisted of 80% of the new building addition and was completed in December of 1999. The Owner then moved out of the old three story into the new addition. The old building was demolished and built in it's place was the office, cafeteria and kitchen areas.
The concrete gym building was renovated with new locker rooms on the lower level and a refurbished gym on the upper level. An exterior plaster coating system was used on the gym exterior to improve the appearance and make it water tight.
Owner:
Ogden Community School District
Size: 43,550 SF
Completed:
2000
Cost per SF: $82.93